jedsouth
Regular Member
Thought I'd start a new thread for our area.
Save posting and hanging as have done for many months in the other area threads.
More Toob transit vans in our area this week.
Just had a chat with one of them. He had all the blue cables and hub out of the Toob pavement trap and was working on it inside the van, connected up to monitor.
Asked him how long for here.
He said August is looking very likely for our Go live. Expects June and July to still be doing this kind of testing and correction.
They are now testing speed and power to base for all the main runs.
So far looking good, but this last month or two is normally needed also to rectify or adjust the Contractors connection errors.
Much the same as that pole wire and pole dp connecting team a months or so said.
He mentioned its on track here, not like Eastleigh area that has hardly started yet and East Southampton, where a lot of extra build work still needs to be completed.
Sounding good for us...
Save posting and hanging as have done for many months in the other area threads.
More Toob transit vans in our area this week.
Just had a chat with one of them. He had all the blue cables and hub out of the Toob pavement trap and was working on it inside the van, connected up to monitor.
Asked him how long for here.
He said August is looking very likely for our Go live. Expects June and July to still be doing this kind of testing and correction.
They are now testing speed and power to base for all the main runs.
So far looking good, but this last month or two is normally needed also to rectify or adjust the Contractors connection errors.
Much the same as that pole wire and pole dp connecting team a months or so said.
He mentioned its on track here, not like Eastleigh area that has hardly started yet and East Southampton, where a lot of extra build work still needs to be completed.
Sounding good for us...























