The UK Government (DSIT / BDUK) has today posted a small-ish modification to Openreach’s Call-Off 2 Project Gigabit broadband roll-out contract for Devon, Mid Wales and South East Wales. The change reduces the contracted scope of their network build by removing 2,157 premises from the plan, which also reduces the allocated public funding by £3.9 million.
Just to recap. The Call-off 2 contract was previously backed by a public investment of £137.27m and aimed to extend Openreach’s full fibre (FTTP) broadband network to a further 41,144 premises in hard-to-reach areas (i.e. usually remote rural locations that had been left neglected by commercial deployments).
Call-off 2 is a Cross-Regional (Type C) procurement, which typically reflects remote rural areas where no or no appropriate market interest has previously been expressed before to the Government’s Building Digital UK (BDUK) team, or areas that have been de-scoped or terminated from a prior procurement. Only Openreach does Type C via their Single Supplier Framework deal – now valued at up to c.£2.346bn.
Advertisement
According to the latest BDUK status update from November 2026 (here), Openreach has so far built to 15,040 of the contracted premises under call-off 2 (c.38% completed). However, such contracts are not static and their scope, as well as committed levels of public funding, can change over time for a number of different reasons.
For example, commercial operators may expand or reduce their roll-out plans in the same region(s), which can reduce or grow the scope for public investment within those same areas. The contracted operator could also find part of the deployment to be more expensive, or possibly even cheaper, than previously envisaged. In this case call-off 2, after the scope reduction, is now valued at £133,370,981 and will aim to cover 38,987 premises.
The catch is that there may be further changes in the future, which could go in a different direction. So, it is not always easy to tell what the final picture will be until you actually reach the end of each contracted build. As usual there are no specific details of which areas have been removed from the plan in this update.
Advertisement
Which premises? Is there anywhere that shows where they are building to?
I guess if Openreach are turning down £1,800 per property then these must be very hard to reach, and they’ve opted not to bother.
It seems unlikely to be descoped for the other reason, i.e. now in scope of some commercial network rollout.
I do wonder how much of the original contract was on a blended price, and whether there’s some cherry-picking going on.