Posted: 19th Apr, 2004 By: Ian
Samknows is reporting that 4 exchanges RFS dates have been delayed.
Exchange Old date New date Reason
Abbots Bromley 21/04/2004 25/08/2004 New CJ cable required
Glenfarg 21/04/2004 26/05/2004 Delay to SDH ring provision
Kimbolton 02/06/2004 29/09/2004 New CJ cable and duct required
Stelling Minnis 02/06/2004 22/12/2004 Cable delay, will not be ready until December"
The BT campaign team will apparently be having "urgent discussions with the planning teams to assess the situation and the impact (if any) on future dates."We hope that the meeting taking place isn't a meeting that is forecasting anymore RFS delays!
More @